HomeAbout IslesFeedbackStatistics User: Guest (Public) | Saturday, 20 January 2018 
Gulhi
Inhabited Island
Kaafu Atoll
North Central Province
Project Category






Post Tsunami recovery and reconstruction project - School Upgrading
Categories:  Education
Implementing Agency: Ministry of Education
Executing Agency: - n/a
Start Date: 11/09/2006
Expected Completion Date: 02/06/2007
Financial Source(s): World Bank
Cost: Rf  538,033.29
Summary: construction works completed. final inspection done and retention held. retention period completed 2-3-2008
Project Status in Island: Completed
Overall Project Status: On-going
Construction of New Classrooms in Single session Schools
Categories:  Education
Implementing Agency: The President's Office
Executing Agency: Ministry of Education
Start Date: 05/06/2009
Expected Completion Date: 15/11/2009
Financial Source(s): Government of Maldives
Community contribution
Cost: Rf  988,932.50
Summary: - Construction of 4 classrooms completed, and furniture supplied.
* contractor: Prop pvt ltd
Project Status in Island: Completed
Overall Project Status: On-going
Government of Maldives - 2018