HomeAbout IslesFeedbackStatistics User: Guest (Public) | Saturday, 20 January 2018 
Himmafushi
Inhabited Island
Kaafu Atoll
North Central Province
Project Category














Construction of K. Hinmafushi Mosque
Categories:  Infrastructure Building
Implementing Agency: Ministry of Islamic Affairs
Executing Agency: - n/a
Start Date: 16/08/2007
Expected Completion Date: 31/05/2010
Financial Source(s): Government of Maldives
Cost: Rf  4,076,129.00
Summary: Overall project progress 85% completed.
- All works of the project is finished. Except paving works

Delays:
- Contractor faced cash flow problems and some scope changes.
Project Status in Island: On-going
Overall Project Status: On-going