Hulhumale' Road Development Project 2010.
|
|
Categories:
|
Transportation
|
|
Implementing Agency:
|
Housing Development Corporation (HDC)
|
|
Executing Agency:
|
Ministry of Housing and Environment
|
|
Start Date:
|
08/04/2010
|
|
Expected Completion Date:
|
02/10/2011
|
|
Financial Source(s):
|
Housing Developing Coporation
|
|
Cost:
|
Rf 41,418,543.95
|
|
Summary:
|
*Overall project 62% completed.
Progress Details : 1. Map P, compaction works 98% completed. 2. Map M, compaction works 98% completed. 3. Map L, kerb laying works going on, 99% of the A-kerb laying completed. 4. Map L subgrade compaction 98% completed. 5. MWSC sewer and water crossings completed in Map L & P, and Map M all water & sewer completed. 6. Map P is almost ready for ABC laying. 7. Map L and P around 90% of the Stelco & Dhiraagu crossing completed & Map M is 100% completed. 8. Map P, 90% of A-Kerb completed & B-kerb 50% completed. 9. Map L, B-kerb 99% completed. 10. Map L, greening area and water outlet 99% completed. 11. Map M, 75% of A-kerb completed. 12. All the subgrade tests are completed. 13. Bitumen has arrived on site 14. Map M, 70% of B-kerb completed. 15. Map L, Road 1, 2 & 3, 90% of ABC work completed. 16. Casting foundation for installation of Ashphalt batching plant 17. Placing of junction boxes at Map L, 80% completed. 18. Installation of Asphalt plant going on
Delays: 1. Materials not available, causing delay in submission for approval. 2. Mobilisation delays by the contractor 3. Project will have a major delay, since MTCC does not have asphalt plant. 4.Due to quota problem contractor is having difficulty in getting required material for the project
|
|
Project Status in Island:
|
On-going
|
|
Overall Project Status:
|
On-going
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|