Hulhumale'
Inhabited Island
Male' Atoll
Capital
Project Category


















FISH PROCESSING FACTORY/ICE PLANT
Categories:  Fisheries
Implementing Agency: - n/a
Executing Agency: - n/a
Start Date:
Expected Completion Date:
Financial Source(s): Impacs
Cost:  
Summary:
Project Status in Island: Completed
Overall Project Status: Completed
Feasibility study for application of photovoltaic power on male’ and hulhumale’ islands
Categories:  Utilities: Electricity
Implementing Agency: Ministry of Housing and Environment
Executing Agency: Ministry of Finance and Treasury
Start Date:
Expected Completion Date:
Financial Source(s): Japan Government
Cost:  
Summary: feasibility study report has been completed
Project Status in Island: Completed
Overall Project Status: Completed
Construction of Hulhumale 504 Housing units
Categories:  Housing
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: - n/a
Start Date: 17/10/2006
Expected Completion Date: 29/02/2008
Financial Source(s):
Cost: US$  10,000,000.00
Summary: - 488 Flats completed and allocated. - 15 flats reserved for government and occupation of these flats are pending, thus HDC is incuring losses
Project Status in Island: Completed
Overall Project Status: Completed
Hulhumale' Waste Yard Development Project 2010
Categories:  Waste Management
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: Ministry of Housing and Environment
Start Date: 01/03/2010
Expected Completion Date: 05/09/2010
Financial Source(s): Housing Developing Coporation
Cost: Rf  2,942,989.28
Summary: * Overall project 100% completed.
* Project defects liability period starts from 5th September 2010 and will be end by 4th September 2011.
* Project has been delayed 37 days due to inclement weather, increased scope of works and design modification.
Project Status in Island: Completed
Overall Project Status: Completed
Hulhumale' - Hulhule Road Construction Project 2009.
Categories:  Transportation
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: Ministry of Housing and Environment
Start Date: 19/08/2010
Expected Completion Date: 26/11/2010
Financial Source(s): Housing Developing Coporation
Cost: Rf  7,500,000.00
Summary: * Overall project 100% completed.
* HDC contributed Rf 2.5 million out RF 7.5 million
* Shortage of materials.
* Faulty machineries and equipments.
Project Status in Island: Completed
Overall Project Status: Completed
Appartment Complex - Hulhumale', Damas Company Pvt Ltd, 90/2010
Categories:  Housing
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: - n/a
Start Date: 23/12/2008
Expected Completion Date: 01/06/2010
Financial Source(s): Investor Finance
Cost:  
Summary: Overall project progress: 100% completed.

Progress Details :
Project has been completed and ready to start selling the apartments.

Delays:
Delayed in approving the detailed drawings.
Project Status in Island: Completed
Overall Project Status: Completed
Developing Hulhumale' Sports Area
Categories:  Sports
Implementing Agency: Ministry of Human Resources, Youth and Sports
Executing Agency: - n/a
Start Date: 01/01/2007
Expected Completion Date: 31/12/2010
Financial Source(s): Government of Maldives
Cost: Rf  2,610,634.66
Summary: - Overall project's 50% completed.
- Court area surface levelling work completed. But the Dhun'gathi project has not been started in the year 2009 and budget has been cancelled as the 2009 came to an end.
- Building basket court was planned in 2010 and due to unavailability of budget, project is delayed

Delays:
- The Finance Ministry has adviced to change the point giving system and re-tender the project
Delays:
- The finance ministry has advised to change the point giving system and to re-tender the project.
Project Status in Island: Delayed
Overall Project Status: Delayed
Apartment Complex - Hulhumale', Rainbow Enterprises Pvt Ltd, 87/2010
Categories:  Housing
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: - n/a
Start Date: 23/12/2008
Expected Completion Date: 17/02/2012
Financial Source(s): Investor Finance
Cost:  
Summary: progress details :
1) Project work has been stopped for a long time. Contrator has informed that they are going to re-start work as soon as possible.
Delays:
1) Due to inaccessible to water and electricity from site.
2) Due to financial crisis.
3) Presence of mud in the site.

Project Status in Island: Delayed
Overall Project Status: Delayed
TECHNICAL ASSISTANCE FOR A NEW HOSPITAL IN HULHUMALE
Categories:  Health
Implementing Agency: Ministry of Health and Family
Executing Agency: Ministry of Health and Family
Start Date: 01/01/2005
Expected Completion Date: 01/08/2010
Financial Source(s): Not Available
Cost: Rf  6,715,263.90
Summary: The consultant has visited Maldives to do a review on the information needed to do the fesibility study.
Project Status in Island: On-going
Overall Project Status: On-going
Hulhumale Phase 2- Special economic Zone
Categories:  Infrastructure Building
Implementing Agency: - n/a
Executing Agency: - n/a
Start Date:
Expected Completion Date:
Financial Source(s): Dubai World
Cost:  
Summary: Approved by National Planning Council.
Project Status in Island: On-going
Overall Project Status: On-going
10,000 HOUSING UNITS PROGRAMME (1700 HOUSING UNITS IN HULHUMALE') - Hulhumale' Row House Project 2010 - 12 Row Houses.
Categories:  Housing
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: Ministry of Housing and Environment
Start Date: 13/05/2010
Expected Completion Date: 31/05/2011
Financial Source(s): Housing Developing Coporation
Cost: Rf  16,077,109.51
Summary: Overall project 91% completed.

Prgoress Details:
1. Putty work at plot A 2nd floor 100% & plot B 99%completed.
2. Plastering completed.
3. Floor Screeding completed.
4. Electrical wiring completed.
5. Ceiling work Plot A 100% and plot B 100% completed.
6. Glass block laying at plot A 75% and plot B 50% completed.
7. T & B Waterproofing Plot A 100% completed.
8. Plot A floor tiling work 100% completd and plot B 100%.
9. Plot B metal railing 80% completed & plot A 90%.
Glass block laying at plot A 75% and plot B 50% completed.
10.Plot A & B external painting 85% completed.
11. Plumbing work at G.Floor plot A 100% & plot B 100% completed.
12. Plot A wall tiling toilet 99% & plot B 99%completed.
13. Plot B water pressure test 100% completed.
14. Plot A kitchen top tiling 100% & plot B 85% completed.
15. Plot A door frame 100% & plot B 100% completed.
16. Inspection chamber plastering plot B 25% & plot A 50%.
17. Fire alarm system plot A & B 40%.
18. Plot A door pannel installation 100% & plot B 10% completed.

Delays:
Delayed for 35 days due to bad weather conditions
Project Status in Island: On-going
Overall Project Status: On-going
Hulhumale' Road Development Project 2010.
Categories:  Transportation
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: Ministry of Housing and Environment
Start Date: 08/04/2010
Expected Completion Date: 02/10/2011
Financial Source(s): Housing Developing Coporation
Cost: Rf  41,418,543.95
Summary: *Overall project 62% completed.

Progress Details :
1. Map P, compaction works 98% completed.
2. Map M, compaction works 98% completed.
3. Map L, kerb laying works going on, 99% of the A-kerb laying completed.
4. Map L subgrade compaction 98% completed.
5. MWSC sewer and water crossings completed in Map L & P, and Map M all water & sewer completed.
6. Map P is almost ready for ABC laying.
7. Map L and P around 90% of the Stelco & Dhiraagu crossing completed & Map M is 100% completed.
8. Map P, 90% of A-Kerb completed & B-kerb 50% completed.
9. Map L, B-kerb 99% completed.
10. Map L, greening area and water outlet 99% completed.
11. Map M, 75% of A-kerb completed.
12. All the subgrade tests are completed.
13. Bitumen has arrived on site
14. Map M, 70% of B-kerb completed.
15. Map L, Road 1, 2 & 3, 90% of ABC work completed.
16. Casting foundation for installation of Ashphalt batching plant
17. Placing of junction boxes at Map L, 80% completed.
18. Installation of Asphalt plant going on

Delays:
1. Materials not available, causing delay in submission for approval.
2. Mobilisation delays by the contractor
3. Project will have a major delay, since MTCC does not have asphalt plant.
4.Due to quota problem contractor is having difficulty in getting required material for the project
Project Status in Island: On-going
Overall Project Status: On-going
10,000 HOUSING UNITS PROGRAMME (1700 HOUSING UNITS IN HULHUMALE') - Coral Ville- Construction of 1st Phase (180 Units) of the proeject.
Categories:  Housing
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: - n/a
Start Date: 01/07/2010
Expected Completion Date: 28/02/2012
Financial Source(s):
Cost:  
Summary: Overall project : 55% completed.

Progress Details:
1) 95% of C1 block construction works are completed
2) 92% of C2 block construction works are completed
3) 92% of C3 block construction works are completed
4) 92% of C4 block construction works are completed
5) 92% of C5 block construction works are completed
6) 92% of C6 block construction works are completed
7) 92% of C7 block construction works are completed
8) 92% of C8 block construction works are completed
9) 92% of C9 block construction works are completed

Delays:
1) Delayed in getting labour quota
2) Completion date was delayed since the finsihing works of the C1 and C2 need to be re-do as the quality control officer did not approve the work.
Project Status in Island: On-going
Overall Project Status: On-going
Condominium Housing- Platinum Capital Holdings Pvt Ltd.
Categories:  Housing
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: Ministry of Housing and Environment
Start Date: 26/09/2006
Expected Completion Date: 31/07/2011
Financial Source(s): Investor Finance
Cost:  
Summary: Progress details:
1) Project to be completed in two phases; Phase I to be completed by the end of June 2010 and Phase II by the end of June 2013.
2) Extension given to complete the phase I of the project till the end of July 2011 upon request. Revised performance guarantee is yet to be submitted.
3) Vast progress of the project observed on the plot. Ownership of plot transferred to Platinum Real Estate Development Pvt Ltd on 2-Feb-11.

Delays:
1. According to PCH, delays were mainly due to financial difficulties, which they have managed to overcome through an agreement they have entered into with Platinum Real Estate Development Pvt
Project Status in Island: On-going
Overall Project Status: On-going
Condominium Housing- Villa Shipping and Trading Company Pvt Ltd.
Categories:  Housing
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: Ministry of Housing and Environment
Start Date: 30/06/2010
Expected Completion Date: 31/08/2011
Financial Source(s): Investor Finance
Cost:  
Summary: Progress Details:
The agreement between Villa and HDC has been terminated by HDC due to poor performance

Delays:
1. Project has been delayed by 4 years. Villa claims financial difficulties. Due to the lack of progress the objectives remains unfulfilled. There is no certainty that the project could be delivered within new timelines.
2. Villa informed on 10th November 2010, that the delay was caused by recent recession.
Project Status in Island: On-going
Overall Project Status: Stopped
Steel Structure - 02 Storey Garage Units Building in Hulhumalé, Industrial Zone.
Categories:  Infrastructure Building
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: Ministry of Housing and Environment
Start Date: 10/11/2009
Expected Completion Date: 24/04/2011
Financial Source(s): Housing Developing Coporation
Cost: Rf  5,666,450.00
Summary: Overall project 80% completed.

Progress Details:
1) 100% of masonry works are completed
2) 99% of plastering works are completed
3) 94% of Electrical works completed
4) 93% of plumbing works completed
5) 87% of inatallation works of staircases are completed
6) 100% of rolloff shutter works are done.
7) 95% of drainage works are completed
8) 65% of tilling works completed
9) 37% of painting is done
10) 49% of doors and windows are installed.

Delays:
1) The project has been delayed due to issues with contractor and currently they are completing the project.
2) Extention has been given to the contractor till to the 24th March 2011, but they were unable to complete the project.
3) Currently HDC is charging penalty for delaying on contractor.
Project Status in Island: On-going
Overall Project Status: On-going
Hulhumale' Commercial Block Development Project 2010.
Categories:  Infrastructure Building
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: - n/a
Start Date: 12/08/2010
Expected Completion Date: 19/01/2011
Financial Source(s): Housing Developing Coporation
Cost: Rf  3,625,886.00
Summary: Overall project 85% completed.

Progress details:
1) Electrical conceal pipe laying at 1st and 2nd floor 100% completed.
2) External & Internal paint sealer works completed..
3) External steel starcase red-oxide painting completed.
4) Roof woks pending due to unavailability of roofing sheets.
5) 1st FL to 2nd FL wooden stair works ongoing.

Delays:
1) Presence of mud in the site, causing delays which was unexpected.
2) Project has been delayed due to unavailability of roofing material from Maldives.
3) Time extension yet to grant.
Project Status in Island: On-going
Overall Project Status: On-going
Appartment Complex - Hulhumale', Jausa Property Development Maldives Pvt Ltd, 89/2010
Categories:  Housing
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: - n/a
Start Date: 23/12/2008
Expected Completion Date: 28/02/2011
Financial Source(s): Investor Finance
Cost:  
Summary: Overall project progress : 100% completed.

Progress Details:
1). Project has been completed and has started selling the apartments.

Delays:
1) Delayed in plot surveying and handing over.
2) Delayed in approving and handing over of temporary land.
3) Delayed in laying foundation due to clay Soil below the sandy soil.
Project Status in Island: On-going
Overall Project Status: Completed
Appartment Complex - Hulhumale', Lexon Pvt Ltd, 91/2010
Categories:  Housing
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: - n/a
Start Date: 14/12/2009
Expected Completion Date: 31/03/2012
Financial Source(s): Investor Finance
Cost:  
Summary: Overall project progress : 30% completed.
1) Ground levelling, setting out and excavtion works are fully completed.
2)100% of foundation works are completed
3) 100% of first floor slab work is completed
4) 100% of second floor slab work is completed
5) 100% of third floor slab work is completed
100% of foundation works are completed
Project Status in Island: On-going
Overall Project Status: On-going
Apartment Complex - Hulhumale', Rainbow Construction Pvt Ltd, 88/2010
Categories:  Housing
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: - n/a
Start Date: 01/06/2010
Expected Completion Date: 01/09/2011
Financial Source(s): Investor Finance
Cost:  
Summary: Overall project progress : 10% completed.

Progress Details :
1) Project work has been stopped for a long time. Contrator has informed that they are going to re-start work as soon as possible.
Project Status in Island: On-going
Overall Project Status: On-going
Male' Atoll Hulhumale' Mosque
Categories:  Infrastructure Building
Implementing Agency: Ministry of Islamic Affairs
Executing Agency: - n/a
Start Date:
Expected Completion Date:
Financial Source(s): Public Sector Investment Program 2010-2012
Cost: US$  1,555,485.00
Summary: - Conditional Approval by National Planning Council.
- Proposed for PSIP 2010
Project Status in Island: Planned
Overall Project Status: Planned
Developing Hulhumale' Youth Centre
Categories:  Infrastructure Building
Implementing Agency: Ministry of Human Resources, Youth and Sports
Executing Agency: - n/a
Start Date:
Expected Completion Date:
Financial Source(s): Public Sector Investment Program 2010-2012
Cost: US$  116,732.00
Summary: Approved by National Planning Council to carry under PPP.
Project Status in Island: Planned
Overall Project Status: On-going
Construction of flats for police staff and for their family
Categories:  Housing  Infrastructure Building
Implementing Agency: Maldives Police Service (MPS)
Executing Agency: - n/a
Start Date:
Expected Completion Date:
Financial Source(s):
Cost:  
Summary:
Project Status in Island: Planned
Overall Project Status: Planned
10,000 Housing units programme (1700 Units in Hulhumale') - CMEC 1000 Housing Units
Categories:  Housing
Implementing Agency: CHINA NATIONAL MACHINERY & EQUIPMENT IMP.& EXP.CORP. (CMEC,China)
Executing Agency: Ministry of Housing and Environment
Start Date: 21/03/2010
Expected Completion Date:
Financial Source(s): Investor Finance
Cost:  
Summary: Progress Details:
-Excavation in progress
-Temporary shelter equipments already shipped.
Project Status in Island: Planned
Overall Project Status: On-going
Media Related Investment in Hulhumale'/ South West Corner of Hulhumale'- Picture Land FM (SUN FM)
Categories:  Information Communication Technology (ICT)
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: - n/a
Start Date: 06/06/2010
Expected Completion Date: 05/06/2011
Financial Source(s): Investor Finance
Cost:  
Summary: Delays:
The project is getting delayed, since water and electrcicty is not available from there. However, STELCO and MWSC
will be providing the services towards the end of this year.
Project Status in Island: Planned
Overall Project Status: Planned
Media Related Investment in Hulhumale'/South West Corner of Hulhumale' - Fujifilm Digital Imaging (FDI) Station
Categories:  Information Communication Technology (ICT)
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: - n/a
Start Date: 06/06/2010
Expected Completion Date: 06/09/2011
Financial Source(s): Investor Finance
Cost:  
Summary: Delays:
The project is getting delayed, since water and electrcicty is not available from there. However, STELCO and MWSC
will be providing the services towards the end of this year.
Project Status in Island: Planned
Overall Project Status: Planned
Media Related Investment in Hulhumale'.South West Corner of Hulhumale'. - Novelty Printers and Publishers Pvt Ltd
Categories:  Information Communication Technology (ICT)
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: - n/a
Start Date: 06/06/2010
Expected Completion Date: 06/06/2011
Financial Source(s): Investor Finance
Cost:  
Summary: Delays:
The project is getting delayed, since water and electrcicty is not available from there. However, STELCO and MWSC
will be providing the services towards the end of this year.
Project Status in Island: Planned
Overall Project Status: Planned
Media Related Investment in Hulhumale'/South West Corner of Hulhumale'. - Island Broad Casting Company Pvt Ltd (VTV)
Categories:  Information Communication Technology (ICT)
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: - n/a
Start Date: 06/06/2010
Expected Completion Date: 06/06/2011
Financial Source(s): Investor Finance
Cost:  
Summary: Delays:
The project is getting delayed, since water and electrcicty is not available from there. However, STELCO and MWSC
will be providing the services towards the end of this year.
Project Status in Island: Planned
Overall Project Status: Planned
Media Related Investment in Hulhumale'/South West Corner of Hulhumale'. - Media Net Pvt Ltd
Categories:  Information Communication Technology (ICT)
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: - n/a
Start Date: 06/06/2010
Expected Completion Date: 06/09/2011
Financial Source(s): Investor Finance
Cost:  
Summary: Delays:
The project is getting delayed, since water and electrcicty is not available from there. However, STELCO and MWSC
will be providing the services towards the end of this year.
Project Status in Island: Planned
Overall Project Status: Delayed
Media Related Investment in Hulhumale'/South West Corner of Hulhumale'.- Techno Media Pvt Ltd.
Categories:  Information Communication Technology (ICT)
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: - n/a
Start Date: 06/06/2010
Expected Completion Date: 06/09/2011
Financial Source(s): Investor Finance
Cost:  
Summary: Progress Details :
Detail drawings have been submitted for approval.

Delays:
The project is getting delayed, since water and electrcicty is not available from there. However, STELCO and MWSC
will be providing the services towards the end of this year.
Project Status in Island: Planned
Overall Project Status: Planned
Media Related Investment in Hulhumale'/South West Corner of Hulhumale'. - B-Cube Signage Maldives Pvt Ltd
Categories:  Information Communication Technology (ICT)
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: - n/a
Start Date: 02/09/2010
Expected Completion Date: 02/09/2011
Financial Source(s): Investor Finance
Cost:  
Summary: Delays:
The project is getting delayed, since water and electrcicty is not available from there. However, STELCO and MWSC
will be providing the services towards the end of this year.
Project Status in Island: Planned
Overall Project Status: Planned
Ferry Terminal Park - Near Hulhumale' Ferry terminal.
Categories:  Transportation
Implementing Agency: Housing Development Corporation (HDC)
Executing Agency: - n/a
Start Date: 03/01/2010
Expected Completion Date: 30/11/2010
Financial Source(s): Housing Developing Coporation
Cost:  
Summary: Overall project progress 75% completed.

Progress Details :
1) 100% of the building works of 2 kiosks and huts are done.
2) 35% of the landscaping is completed.
3) Land Cultivating works going on.

Delays :
Delayed getting fertilizers for the landscaping.
Project Status in Island: Planned
Overall Project Status: On-going