Gaafaru
Inhabited Island
Kaafu Atoll
North Central Province
Project Category
















Post Tsunami recovery and reconstruction project - School Upgrading
Categories:  Education
Implementing Agency: Ministry of Education
Executing Agency: - n/a
Start Date: 20/09/2006
Expected Completion Date: 18/02/2007
Financial Source(s): World Bank
Cost: Rf  1,021,428.20
Summary: Project completed
Project Status in Island: Completed
Overall Project Status: On-going
BOAFEN HIDHUMAI MASHROOU-Phase 1
Categories:  Utilities: Water
Implementing Agency: The President's Office
Executing Agency: - n/a
Start Date: 01/05/2005
Expected Completion Date:
Financial Source(s): International Federation of Red Cross and Red Crescent Societies (IFRC).
Cost:  
Summary: Provided 2500 ltr water tank for 148 house in the island
Project Status in Island: Completed
Overall Project Status: Completed
75MW Maldives Wind Farm Project - K.Gaafaru
Categories:  Utilities: Electricity  Utilities: Renewable Energy
Implementing Agency: Ministry of Housing and Environment
Executing Agency: State Electrical Company (STELCO)
Start Date:
Expected Completion Date:
Financial Source(s): Falcon Energy
Cost: US$  200,000,000.00
Summary: Approved by National Planning Council to establish the wind farm

NPC Decision as on 15/10/2009:
- The aim of this project is making Maldives a Carbon Neutral Country, inform the investor to establish the Wind mast in K.Gaafaru in an immediate period that MHTE agrees.
- Find Maldivian Companies in finding contractors for doing Civil Works other than Reclamation work.
- To send regularly update to NPC of the ongoing pre-preparation and the implementing stage of the project.
Project Status in Island: On-going
Overall Project Status: On-going
Nationwide Transport System North Central Province
Categories:  Transportation
Implementing Agency: Ministry of Housing and Environment
Executing Agency: MTCC
Start Date: 15/03/2010
Expected Completion Date:
Financial Source(s): MTCC
Cost:  
Summary: - Agreement signed on 7th October 2009 with MTCC.
- Temporary service started on
• K.Atoll 15th March 2010
• K. Atoll (south) 1st April 2010
Project Status in Island: On-going
Overall Project Status: On-going
Installation of desalination plant in the islands
Categories:  Utilities: Water
Implementing Agency: Ministry of Housing and Environment
Executing Agency: - n/a
Start Date:
Expected Completion Date:
Financial Source(s): UNICEF
Cost:  
Summary: - Desalination plant is not yet installed with a capacity of 10 ton.
- It is planned to buid a plant house.
- Service not yet started because house plant is not built.
Project Status in Island: On-going
Overall Project Status: On-going
To implement Telemedicine Kiosk network in 35 islands
Categories:  Health
Implementing Agency: Ministry of Health and Family
Executing Agency: Ministry of Health and Family
Start Date: 01/02/2010
Expected Completion Date: 31/12/2012
Financial Source(s): Abu Dhabi Khaleefa Foundation
Cost: US$  5,800,000.00
Summary: Implementation of selected Kiosk technology in the 3 central hospitals and 7 rural islands in the first year. 2) Complete the training component for the phase 1 3) Provide Connectivity to these referral islands 4) Develop clear protocols, standards and guidelines for the use of this technology 5) Sensitization and training of users as well as stakeholders Objectives: * Provide accessible, high-quality medical care to small, isolated populations. * Provide physician-prescribed, accessible, and audited telepharmacy services to small villages with no pharmacy. * Provide accessible, high-quality clinical blood laboratory services to small,isolated populations. * Provide specialized medical support to remotely-located general physicians and healthcare workers. * Establish a network of services through which the medical records of enrolled patients can be electronically transferred and viewed by multiple physicians and medical practitioners over the archipelago and abroad.
Project Status in Island: On-going
Overall Project Status: On-going
Construction of K. Gaafaru Mosque
Categories:  Infrastructure Building
Implementing Agency: The President's Office
Executing Agency: Ministry of Islamic Affairs
Start Date: 01/10/2012
Expected Completion Date: 09/10/2013
Financial Source(s):
Cost:  
Summary: Construction of K. Gaafaru Mosque
Project Status in Island: On-going
Overall Project Status: On-going
10,000 Housing Units Programme-Planned (7,000 units in Provinces)
Categories:  Housing
Implementing Agency: Ministry of Housing and Environment
Executing Agency: Ministry of Housing and Environment
Start Date:
Expected Completion Date:
Financial Source(s):
Cost:  
Summary: 50 units.
Project Status in Island: Planned