Gulhi
Inhabited Island
Kaafu Atoll
North Central Province
Project Category






Post Tsunami recovery and reconstruction project - School Upgrading
Categories:  Education
Implementing Agency: Ministry of Education
Executing Agency: - n/a
Start Date: 11/09/2006
Expected Completion Date: 02/06/2007
Financial Source(s): World Bank
Cost: Rf  538,033.29
Summary: construction works completed. final inspection done and retention held. retention period completed 2-3-2008
Project Status in Island: Completed
Overall Project Status: On-going
BOAFEN HIDHUMAI MASHROOU-Phase 1
Categories:  Utilities: Water
Implementing Agency: The President's Office
Executing Agency: - n/a
Start Date: 01/05/2005
Expected Completion Date:
Financial Source(s): International Federation of Red Cross and Red Crescent Societies (IFRC).
Cost:  
Summary: Provided 2500 ltr water tank for 88 house in the island
Project Status in Island: Completed
Overall Project Status: Completed
Construction of New Classrooms in Single session Schools
Categories:  Education
Implementing Agency: The President's Office
Executing Agency: Ministry of Education
Start Date: 05/06/2009
Expected Completion Date: 15/11/2009
Financial Source(s): Government of Maldives
Community contribution
Cost: Rf  988,932.50
Summary: - Construction of 4 classrooms completed, and furniture supplied.
* contractor: Prop pvt ltd
Project Status in Island: Completed
Overall Project Status: On-going
Nationwide Transport System North Central Province
Categories:  Transportation
Implementing Agency: Ministry of Housing and Environment
Executing Agency: MTCC
Start Date: 15/03/2010
Expected Completion Date:
Financial Source(s): MTCC
Cost:  
Summary: - Agreement signed on 7th October 2009 with MTCC.
- Temporary service started on
• K.Atoll 15th March 2010
• K. Atoll (south) 1st April 2010
Project Status in Island: On-going
Overall Project Status: On-going