Post Tsunami recovery and reconstruction project - School Upgrading
Categories:
Education
Implementing Agency:
Ministry of Education
Executing Agency:
- n/a
Start Date:
22/08/2006
Expected Completion Date:
19/11/2006
Financial Source(s):
World Bank
Cost:
Rf 545,564.85
Summary:
final inspection done and retention held.
Project Status in Island:
Completed
Overall Project Status:
On-going
Indian Ocean Tsunami Relief Emergency- ELECTRICITY
Categories:
Utilities: Electricity
Implementing Agency:
- n/a
Executing Agency:
- n/a
Start Date:
16/05/2007
Expected Completion Date:
01/03/2009
Financial Source(s):
US Aid
Cost:
Summary:
Handed Over to RK. Committee
Project Status in Island:
Completed
Overall Project Status:
Completed
BOAFEN HIDHUMAI MASHROOU-Phase 1
Categories:
Utilities: Water
Implementing Agency:
The President's Office
Executing Agency:
- n/a
Start Date:
01/05/2005
Expected Completion Date:
Financial Source(s):
International Federation of Red Cross and Red Crescent Societies (IFRC).
Cost:
Summary:
Provided 2500 ltr water tank for 124 house in the island
Project Status in Island:
Completed
Overall Project Status:
Completed
Construction of New Classrooms in Single session Schools
Categories:
Education
Implementing Agency:
The President's Office
Executing Agency:
Ministry of Education
Start Date:
02/04/2009
Expected Completion Date:
30/01/2009
Financial Source(s):
Government of Maldives
Cost:
Rf 58,000.00
Summary:
- Construction of classrooms completed, and furniture supplied.
* contractor: Dh. Maaeboodhoo School
Project Status in Island:
Completed
Overall Project Status:
On-going
Desgin and build of sewerage Facilities in 10 islands
Categories:
Utilities: Sewerage
Implementing Agency:
Ministry of Housing and Environment
Executing Agency:
- n/a
Start Date:
Expected Completion Date:
Financial Source(s):
Cost:
Summary:
- Invitation for Bid advertised for design and build of sewerage facilties in the islands through Finance Ministry.
- Bid opening held on 3rd August 2010, Bid evalutaion and negotiation held on 13th October 2010
- Bid submitted by 1 party to 3 islands.
- Bid not yet submitted to 7 islands.
- Termination of bids requested to Tender board.
Project Status in Island:
Planned
Overall Project Status:
Planned