Kibidhoo
Inhabited Island
Thaa Atoll
Inhabited Islands in Atoll:
Buruni
Dhiyamigili
Gaadhiffushi
Guraidhoo
Hirilandhoo
Kadoodhoo
Kibidhoo
Madifushi
Omadhoo
Thimarafushi
Vandhoo
Veymandoo
Vilufushi
South Central Province
Project Category
Profile
Projects
Post Tsunami recovery and reconstruction project - School Upgrading
Categories:
Education
Implementing Agency:
Ministry of Education
Executing Agency:
- n/a
Start Date:
16/11/2006
Expected Completion Date:
13/02/2007
Financial Source(s):
World Bank
Cost:
Rf 812,675.65
Summary:
final inspection done and retention held.
Project Status in Island:
Completed
Overall Project Status:
On-going
BOAFEN HIDHUMAI MASHROOU-Phase 1
Categories:
Utilities: Water
Implementing Agency:
The President's Office
Executing Agency:
- n/a
Start Date:
01/05/2005
Expected Completion Date:
Financial Source(s):
International Federation of Red Cross and Red Crescent Societies (IFRC).
Cost:
Summary:
Provided 2500 ltr water tank for 153 house in the island
Project Status in Island:
Completed
Overall Project Status:
Completed
Tsunami Reconstruction and Livelihood Programme
Categories:
Waste Management
Implementing Agency:
Ministry of Housing and Environment
Executing Agency:
- n/a
Start Date:
Expected Completion Date:
Financial Source(s):
UNDP
Cost:
Summary:
construction of waste management centres and comunity mobilisation programme is completed
Project Status in Island:
Completed
Overall Project Status:
Completed
Construction of New Classrooms in Single session Schools
Categories:
Education
Implementing Agency:
The President's Office
Executing Agency:
Ministry of Education
Start Date:
11/05/2009
Expected Completion Date:
31/03/2010
Financial Source(s):
Government of Maldives
Cost:
Rf 819,999.00
Summary:
- Construction of 2 classrooms completed, and furniture supplied.
* contractor: Mohamed Moosa Noovilaage
Project Status in Island:
Completed
Overall Project Status:
On-going
POST TSUNAMI AGRICULTURE AND FISHERIES REHABILITAION PROGRAMME
Categories:
Fisheries
Agriculture
Implementing Agency:
PIU
Executing Agency:
Ministry of Fisheries and Agriculture
Start Date:
01/01/2006
Expected Completion Date:
30/06/2011
Financial Source(s):
International Fund for Agricultural Development (IFAD)
Cost:
Rf 79,370.00
Summary:
Working in finding a CBPO trainer
Project Status in Island:
On-going
Overall Project Status:
On-going
Nationwide Transport System South Central Province
Categories:
Transportation
Implementing Agency:
Ministry of Housing and Environment
Executing Agency:
Maldives Dhoni Sevices
Start Date:
10/09/2009
Expected Completion Date:
Financial Source(s):
Maldives Dhoni Services
Cost:
Summary:
- Agreement Signed on 6th August 2009 with Maldives Dhoni Services.
- Temporary service started on 10th September 2009 and cover whole Province.
Project Status in Island:
On-going
Overall Project Status:
On-going
Desgin and build of sewerage Facilities in 10 islands
Categories:
Utilities: Sewerage
Implementing Agency:
Ministry of Housing and Environment
Executing Agency:
- n/a
Start Date:
Expected Completion Date:
Financial Source(s):
Cost:
Summary:
- Invitation for Bid advertised for design and build of sewerage facilties in the islands through Finance Ministry.
- Bid opening held on 3rd August 2010, Bid evalutaion and negotiation held on 13th October 2010
- Bid submitted by 1 party to 3 islands.
- Bid not yet submitted to 7 islands.
- Termination of bids requested to Tender board.
Project Status in Island:
Planned
Overall Project Status:
Planned
Kin'bidhoo Agricultural Project (KAP)
Categories:
Agriculture
Implementing Agency:
Th.Kin'bindhoo Zuvaanunge Gulhun
Executing Agency:
Th.Kin'bindhoo Zuvaanunge Gulhun
Start Date:
Expected Completion Date:
Financial Source(s):
Community contribution
Japanese Food Aid and Counterpart Fund
Cost:
Rf 197,067.60
Summary:
Approved by National Planning Council.
Project Status in Island:
Planned
Overall Project Status:
Planned
10,000 Housing Units Programme-Planned (7,000 units in Provinces)
Categories:
Housing
Implementing Agency:
Ministry of Housing and Environment
Executing Agency:
Ministry of Housing and Environment
Start Date:
Expected Completion Date:
Financial Source(s):
Cost:
Summary:
50 units
Project Status in Island:
Planned
Overall Project Status:
Planned
Maldives public infrastructure project. (Harbour Construction component) Contractor finance
Categories:
Harbour
Implementing Agency:
Ministry of Housing and Environment
Executing Agency:
- n/a
Start Date:
Expected Completion Date:
Financial Source(s):
Cost:
US$ 1,894,529.87
Summary:
- Tendering stage
Project Status in Island:
Planned
Overall Project Status:
On-going
Government of Maldives - 2013