ISLES114 - 168 Housing development project in M.Kolhufushi
 
Category(ies):  Housing
Start Date: 10/07/2010 Implementing Agency: The President's Office
Expected Completion Date: 01/02/2012 Executing Agency: - n/a
Cost: Rf  140,326,548.71 Funding Type(s): - Loan
Revised Cost:      
Related Pledges: - Affordable Housing
Financial Source(s): Abu Dhabi Fund
Status: On-going Tag(s): - Project sumbitted to National Planning Council  
Status Description: - Overall project 3% completed.
- Pre-building survey by Contractor completed.
- Demolition and Land clearing works on-going.
- Marking on-site where corners of house will fall - on-going.
- Hiring of Project Consultant at tendering stage.

Delays:
- Delays occur with making contract between resident and Ministry due to court cases, etc.
- Delays occur with Contractor's work starting as residents wanted time to remove their personal belongings from site.
Summary Scope of the project:
- Project scope includes building of 168 houses (including demolition and clearing of land)
- Design and Installation of a Sewerage System (not inclusive in project scope of current contractor)
- Design and Installation of a Clean Water System (not inclusive in project scope of current contractor)
- Design and Installation of an Electrical System (not inclusive in project scope of current contractor)
contractor : MTCC
Added By: Usama Mohamed Rasheed - 23/08/2009 11:56:58 AM
Last Edited By:  Mariyam Azleema - 02/08/2012 10:15:50 AM


Last Edited By: Ibrahim Haleem - 01/07/2012 10:45:14

#IslandAtollStatusStart DateExpected End DateCostFinancial Source(s)Details
1 KolhufushiMeemuOn-going10/07/201001/02/2012 Rf  140,326,548.71 - Abu Dhabi Fund
- Overall project 3% completed. - Pre-building survey by Contractor completed. - Demolition and Land clearing works on-going. - Marking on-site where corners of house will fall - on-going. - Hiring of Project Consultant at tendering stage. Delays: - Delays occur with making contract between resident and Ministry due to court cases, etc. - Delays occur with Contractor's work starting as residents wanted time to remove their personal belongings from site.
Government of Maldives - 2013