ISLES1152 - 2 Storey Warehouse Building in Hulhumale'. CENTEX Group Pvt. Ltd (83/2010).
 
Category(ies):  Infrastructure Building
Start Date: 10/11/2009 Implementing Agency: Housing Development Corporation (HDC)
Expected Completion Date: 24/04/2011 Executing Agency: Housing Development Corporation (HDC)
Cost: Rf  5,666,450.00 Funding Type(s): - Govt. Funded
Revised Cost:      
Related Pledges: - Affordable Housing
Financial Source(s): Government of Maldives
Status: On-going Tag(s): - Project sumbitted to National Planning Council  
Status Description: Overall progress: 50%

Progress:
1) Plumbing works started.
2) Roof sheets laying 100% completed.
3) External and internal wall masonry 55% completed.
4) Erection of stair case started, 15% completed.
5)Floor leveling and reinforcement for floor screeding 70% completed.
6) Masonry works 65% complete.

Delays:
The project has been delayed due to issues with contractor and currently they are completing the project.
Summary Objectives:
1) To provide opportunities to those people who are unable to afford to invest in large scale industrial projects.
2) To enhance the usage rate of industrial zone in Hulhumale'.

Scope of the Project:
1) To develop 10 garage units at the size of 80sqm to conduct light industrial works.
2) To develop surrounding road infrastructure.
Added By: Moosa Haleem - 23/06/2011 09:00:47 AM
Last Edited By:  Moosa Haleem - 23/06/2011 09:09:52 AM