ISLES1203 - Construction of Sh. Milandhoo Magistrate Court
|
|
|
Category(ies):
|
Infrastructure Building
Judicial Services
|
|
|
|
Start Date:
|
16/11/2011
|
Implementing Agency:
|
Office of Programmes and Projects
|
|
Expected Completion Date:
|
26/03/2013
|
Executing Agency:
|
Department of Judicial Administration
|
|
Cost:
|
Rf 3,267,437.79
|
Funding Type(s):
|
-
Govt. Funded
|
|
Revised Cost: |
|
|
|
|
Related Pledges:
|
|
Financial Source(s):
|
|
|
Status:
|
On-going
|
Tag(s):
|
|
|
|
|
|
|
|
Status Description:
|
foundation works, columns works masonary works and roof beam concrete works completed.
Ceilling works, plastering and electrical wiring ongoing
Ceilling works, plastering, counter block work and electrical wiring
|
|
Summary
|
Construction of Sh. Milandhoo Magistrate Court
|
|
|
Added By: Mohamed Hassaan - 13/08/2012 01:42:32 PM